The pool build measured in hours.
A documented Phoenix project coordinated across 22 phases and 150 workers.
One exceptional day. A precisely coordinated build.
The project began at 6 a.m. Excavation moved 85 tons of dirt and was completed in 48 minutes before the remaining trades advanced through the documented sequence.
This was an exceptional, highly coordinated event—not a typical project schedule. Every ordinary pool build depends on its site, design, access, permits, weather, materials, and required inspections.
- 150
- workers
- 22
- phases
- 85
- tons of dirt
- 48
- minutes of excavation
From open ground to Finished water.
Four documented views follow the site through the build.

6 a.m.
Construction begins and the coordinated sequence moves into excavation.

Structure
Crews move through excavation, forming, steel, and the connected construction phases.

Finish
Tile and finish work follow the tightly managed trade sequence.

Complete
The documented build reaches a finished pool in 5 hours, 56 minutes, and 7 seconds.